Park, Project & Facility Updates

Construction Notice for Promontory Community Park:

On Wednesday, March 13, 2019, construction of the new shade structures located at the Promontory Bocce Ball Courts will begin. There will be minimal interruption to programs and events that are occurring at the park during construction. Stay tuned for more project updates and photos.

2019 promontory park construction pic1

2019 promontory park construction pic2

2019 promontory park construction pic3

Tree Replacement at Deputy Jeff Mitchell Field

During the week of February 25, crews were on site at Deputy Jeff Mitchell Field removing 17 diseased Bradford Pear trees. The 17 trees that crews removed were replaced with Liriodendron Trees that are much less susceptible to disease. The Liriodendron Trees (commonly known as Tulip Trees) are fast growing trees that will provide adequate shade for park visitors as they become more mature in size.
2019 tree replacement 1

2019 tree replacement 2


New York Creek Connector Bridge Progress

The New York Creek connector bridge has been progressing well. This new bridge will provide access to pedestrians and bicyclist to and from Silva Valley Parkway and Tam O'Shanter Drive.
2019 new york creek connector bridge preview1

2019 new york creek connector bridge preview2

 

Notice of 2019 Sustainability Project:

Tentative finish date of construction: June 15, 2019, and a Grand Re-Opening Celebration on Wednesday, June 19, 2019.

El Dorado Hills Community Services District is beginning a sustainability project within the next six week to provide solar and LED lighting upgrades to District parks and facilities.

El Dorado Hills Community Park will have new Solar Shade Parking Structures, Solar Thermal at Community Pool, and LED lighting upgrades. Promontory Community Park will have Solar Shade Structures and LED lighting Upgrades. LED Lighting Upgrades will also take place at Oak Knoll Park, Jeff Mitchell Field, Lake Forest Park, Overlook Park, Stephen Harris Park, Governor Park, Kalithea Park, Bertelsen Park, and Art Weisberg Park. This project will save electricity costs and a reduction of 15,000 tons of Green House Gas. 
Click here to see the notice.

The parking lot between the Norm Rowett Pavilion and Teen Center will continue to stay closed. This is to allow accessibility for the construction vehicles. The loop is open only for Fire Department and School Bus access only.

Sustainability Project Updates:

March 25 - 29
Remaining beams and pillars will be placed.

March 18 - 22:
Steel beams have continued to be installed in both Community Park parking lots. Trenching of underground connections has begun as well. A pressure testing inspection of the thermal lines at the Community Pool was successfully completed on Monday.

In coordination with the Energy Project, the Community Park asphalt repair, resealing and restriping project will be taking place. A separate timeline and updates on this project will be included.

March 11 - 15:
A substantial amount of beams were installed at the Community Park and underground work was able to continue due to good weather conditions.

March 4 - 8:
This week included more construction of additional steel beams which are horizontal supports to be installed at the community park.

February 25 - 29:
Weather delayed work on the solar panels at both parks.


February 18 - 22:
The contractor began placing horizontal beams that will house the solar panels. Additional work completed included finishing the plumbing for the thermal at the pool pump room.

February 11 - 15:
The remaining pillars were placed and arms were installed at Community Park and Promontory Community Park.

February 4-8:
A significant amount of steel pillars were erected in both parks as well as the extensions where the solar panels will be placed. Underground work was delayed due to the weather. The pool pump room was plumbed and is ready to accept thermal when that portion of the project is complete. More work includes preparing the thermal equipment at the pool pump room for connection.

January 28 - February 1:
The remaining piers were poured, inspections were made and passed, and steel began being erected throughout the EDH Community Park and Promontory Community Park. A large portion of trenching and conduit was also completed.

January 21-25:
Drilling concluded at both community parks for the pillars, and cages were set for pouring the last 12 piers. Cutting and trenching also began at the parking lot next to Norm Rowett Pavilion. The last delivery of steel was received.

January 14-18:
Contractors work was delayed due to weather resulting in only 2 ½ days of work to be completed. Six semi-truck loads of stell was delivered and the final round of rock drilling was completed on the remaining holes at both promontory Community Park and Community Park. Forming of the bases were set in preparation for pouring concrete. PG&E capped the gas line on Harvard Way to allow for the remaining work to be done at the pool.

January 7-11:
There were 18 more concrete bases poured at Community Park. Promontory Community Park was prepped with shrub removal and drilled for the concreated bases to be poured. More groundwater was found and pumped.

January 2-4:
Despite the wet weather, drilling continued and pouring concrete for the bases began.

December 24 - January 1:
Holiday

December 17-21:
Drilling continued from the previous week at Community Park. It was discovered that several areas had high groundwater and rock. This was worked through and only caused a short delay.

December 10-14:
Equipment for the project arrived, pillars were marked, curbs were cut and drilling began.

December 3-7:
This was the first week
of work for the Sustainability Project. EnPro removed trees and areas were marked for drilling.


sust-rebar

sust-form

sust-beams

sust-forms2

2019 solar project1

2019 solar project2

2018 Solar Project Beam Placement1

2018 Solar Project Structure Beams1

2018 Solar Project Thermal Plumbing

2018 solar project structure 1

2018 solar project structure 2

2018 solar project aerial progress

2018 solar project aerial progress


New York Creek Trail - Capital Improvement Project:

Advance Construction Notification
Information and updates will be continually added.
 
Click here to view the Capital Improvement Program
Click here for information on New York Creek Trail Phase 1
 

 

 

On Wednesday, November 8, 2017, electrostatic painting was completed by Magna-Kote Painting at Kalithea Park on the tubular steel fencing surrounding the west side of the park.

parks make life better

Keep your eye out for an opening of a new District park this year!